Total Float vs. Free float

Difference between Total Float and Free Float

types of float in project management

There are a few types of floats in project management. I will explain the difference between total float and free float in this post. PMP aspirants always get confused with these similar sounding terms. To compound the confusion, the concept of free float is not explained well in many books. In addition to the difference, I will answer the following questions.

  • What is the meaning and definition of different floats?
  • What is the purpose of these floats?
  • What are the important formulas and how do you calculate these floats?

Note: This post is written assuming that you understand the concept of Project Network Diagrams. You have already performed critical path method and have done Forward Pass and Backward Pass to determine Early Start (ES), Late Start (LS), Early Finish (EF) and Late Finish (LF) dates.

Generally speaking Float is also referred to as Slack. In some literature you might find these terms written as Total Slack and Free Slack.

Let us understand the concept with the help of a small example. Refer to the following network diagram.

 

free float and total float

Click To Enlarge

 

Total Float

Total Float (TF) is sometimes simply written as Float.

Total Float is the amount of time an Activity can be delayed without impacting the Project Finish Date.

e.g. if TF for an Activity X is ‘n’ days, it means Activity X can be delayed by ‘n’ days without impacting the Project Finish Date. It can be calculated by using either of the following formulas

TF = LF – EF

OR

TF = LS – ES

Both the formulas will produce same result. e.g. In the above diagram Total Float for Activity A and Activity B are 0 and 1 respectively.

In simple terms we can say that TF is the Flexibility is starting or finishing of an Activity. Here are a few other pertinent points about TF:

  • There is difference between Buffer (Contingency Reserve) and TF. These are not same.
  • It is calculated separately for each activity in the project network diagram. In the above diagram, TF is written in lower middle box for its respective activity.
  • It is calculated for each single activity and not for the entire path.
  • It is shared among the activities that are on the same path. If one activity uses complete TF, the other activities on the same path will have zero TF (i.e. no flexibility). e.g. On Path BF if B uses 1 unit of TF then D will have n0 TF.
  • In a project network, the activities on the Critical Path have least amount of TF. Generally it is zero but it could be negative also. In the above diagram ADE is Critical Path.

 

Free Float

Free Float (FF) is another type of Float.

Free Float is the the amount of time an Activity can be delayed without impacting the Early Start date of any of its Immediate Successors.

e.g. Consider Activity X & Activity Y have a Finish to Start relationship and Activity Y is Successor. If Activity X has a Free Float of ‘n’ days, it means Activity X can be delayed by ‘n’ days without impacting the Early Start of Activity Y. It can be calculated by using one of the following formulas.

FF = min(ES of Successors) – (ES of Activity in Question) – (Duration of Activity in Question)

OR

FF = min(ES of Successors) – (EF of Activity in Question)

The first formula is a generic formula and will work everywhere but the second one will work only if you have used 1 method to do critical path analysis.

Refer to the above network diagram again.

FF for activity A is 0 as any delay in A will delay ES of D.

FF Activity B is 0 as any delay in B will delay ES of F.

FF Activity C is 4 as ES of F will not be impacted till C is delayed by 4 days or less.

Here are a few other pertinent points about FF:

  • Lag and FF are different.
  • FF is useful when there is an imposed start date for a Successor activity.
  • All the Successor activities should be considered while calculating Free Float.
  • TF and FF of an Activity can be different.
  • The above formula for FF is applicable for Finish to Start relationships only.

 

Over To You

Don’t let you mind Float (wander)…Please leave a comment if you are still confused about TF or FF.
 

Related Articles

Difference Between Similar Project Management Terms

More Definitions of Different Types of Float

Praveen Malik, PMP is a certified Project Management Professional (PMP®) with a rich 20+ years of experience. He is a leading Project Management Instructor and Consultant. He regularly conducts Project Management workshops in India & abroad.

2 thoughts on “Total Float vs. Free float

  1. Looks like your description over activity D in the middle, careful!, It’s the activty Duration and it’s not Early Start or ES. Am I right?

    This could confuse the readers.

    Robert A. Romero

  2. Looks like your description over activity D in the middle, careful!, It’s the activty Duration and it’s not Early Start or ES. Am I right?

    This could confuse the readers.

    Robert A. Romero

    August 13, 2011 8:50 PM

Leave a Reply

Your email address will not be published. Required fields are marked *