PD005 – Difference between PMBOK 4th and 5th ed

Previous Post – “PD004 – Difference between PMBOK 4th and 5th ed”

Change XVII

Process Group – Planning / Knowledge Area – Communications 

Instead “Plan Communications” now it is “Plan Communications Management”
Inputs: Project management plan is added. Stakeholder management strategy is removed.

Tools and Techniques: Meetings is newly added.

Change XVIII

Process Group – Planning / Knowledge Area – Risk

“Plan Risk Management” 
Inputs: Project management plan, Project charter and Stakeholder register are newly added. Project scope statement, Cost management plan, Schedule management plan and Communication management plan are removed.

Tools and Techniques: Analytical techniques, Expert judgment and Meetings are newly added. Planning meetings and analysis is removed.

Change XIX

Process Group – Planning / Knowledge Area – Risk

“Identify Risk” 
Inputs: HR Management Plan, Scope Baseline and Procurement documents are newly added.

Change XX

Process Group – Planning / Knowledge Area – Risk

“Perform Qualitative Risk Analysis” 
Inputs: Scope Baseline and Enterprise Environmental Factors are newly added. Project scope statement is removed.

Outputs: Project document updates newly added. Risk register updates is removed.

Change XXI

Process Group – Planning / Knowledge Area – Risk

“Perform Quantitative Risk Analysis” 
Inputs: Enterprise Environmental Factors newly added.

Outputs: Project document updates newly added. Risk register updates removed.

Change XXII

Process Group – Planning / Knowledge Area – Risk

“Plan Risk Response” 
Outputs: Risk register updates and Risk related contract decisions are removed.

Change XXIII
 
Process Group – Planning / Knowledge Area – Procurement

“Plan Procurement Management” 
Inputs: Project management plan and Stakeholder register are newly added. Scope baseline, Teaming agreements, Risk-related contract decisions and Cost performance baseline are removed.

Tools and Techniques: Market Research and Meetings are newly added. Contract types removed.

Outputs: Project documents updates newly added.

Change XXIV

Process Group – Planning / Knowledge Area – Stakeholder [Newly added KA]

“Plan Stakeholder Management” [Newly added process] 
Inputs: Project management plan, Stakeholder register, Enterprise environmental factors and Organizational process assets.

Tools and Techniques: Expert judgment, Meetings and Analytical techniques.

Outputs: Stakeholder management plan and Project document updates

Ramanujam VijayaGopal

PMP Master Prep System

Do you want to become PMP in 50 days? Why don't you start by downloading my free guide? I will give step-by-step guidance and help you in achieving your goal.

Praveen Malik, PMP

Praveen Malik, PMP is a certified Project Management Professional (PMP®) with a rich 23+ years of experience. He is a leading Project Management Instructor and Consultant. He regularly conducts Project Management workshops in India & abroad.

Click Here to Leave a Comment Below

Leave a Reply: