PD004 – Difference between PMBOK 4th and 5th ed

Previous Post – “PD003 – Difference between PMBOK 4th and 5th ed

Change X

Process Group – Planning / Knowledge Area – Time

“Estimate Activity Resources”
Inputs: Schedule Management Plan, Risk registers and Activity Cost Estimate are newly added.


Change XI

Process Group – Planning / Knowledge Area – Time

“Estimate Activity Durations”
Inputs: Schedule Management Plan, Risk registers and Resource Break down structure are newly added.

Tools and Techniques: Group Decision-making techniques is newly added.

Change XII

Process Group – Planning / Knowledge Area – Time

Develop Schedule”
Inputs: Schedule Management Plan, Risk registers, Resource Break down structure and Project staff Assignments are newly added.

Tools and Techniques: Instead of Resource Leveling–, Resource Optimization technique is added. What-if scenario Analysis removed and Modeling Technique is newly added. Instead of Applying Leads and Lags, it is changed to just Leads and Lags.

Outputs: Project calendars and Project Management plan updates are added.

Change XIII

Process Group – Planning / Knowledge Area – Cost

“Plan Cost Management” [Newly added process]
Inputs: Project Management Plan, Project Charter, Enterprise environmental factors and Organizational process assets.

Tools and Techniques: Expert Judgment, Analytical techniques and meetings.

Outputs: Cost Management Plan.

Change XIV

Process Group – Planning / Knowledge Area – Cost

Determine Budget”
Inputs: Cost Management Plan, Risk register and Agreements are newly added.

Outputs: Instead of Cost Performance Baseline, it is changed to Cost Baseline.

Change XV

Process Group – Planning / Knowledge Area – Quality

“Plan Quality Management”
Inputs: Project Management Plan and Requirement Documentation are newly added. Scope baseline, Cost Performance baseline and Schedule Baseline are removed.

Tools and Techniques: Seven Basic Quality tools and Meetings are newly added. Control charts and flowcharting Proprietary Quality Management Methodologies are removed are part of Seven Basic Quality tools.

Change XVI

Process Group – Planning / Knowledge Area – HR

Instead of “Develop HR Plan” now it is “Plan HR Management”
Inputs: Project Management Plan newly added.

Tools and Techniques:Expert Judgment and Meetings are added .

Ramanujam VijayaGopal

PMP Master Prep System

Do you want to become PMP in 50 days? Why don't you start by downloading my free guide? I will give step-by-step guidance and help you in achieving your goal.

Praveen Malik, PMP

Praveen Malik, PMP is a certified Project Management Professional (PMP®) with a rich 23+ years of experience. He is a leading Project Management Instructor and Consultant. He regularly conducts Project Management workshops in India & abroad.

Click Here to Leave a Comment Below

Kristin Anderson Reply

Wow! This is great information that you have shared to us. Indeed, it is really helpful for those who are in their pmp exam prep.

Honey Young Reply

These are the information that is very important. Thank you for sharing the differences of the two editions. pmp flash cards

Leave a Reply: