Category Archives for "Time Management"

time management knowledge area

Critical Path Analysis Example – 2 Ways to Calculate Critical Path

critical path analysis

Critical Path Analysis Example – Using 0 and 1 Method I got introduced to Critical Path Analysis in the year 1997. I am a software engineer by education. I learned most of the project management concepts while managing software projects – Critical Path Analysis was one such concept. I learned about Critical Path while using […]

Continue reading

Why do we need Start to Finish Relationship?

Start to Finish

Start to Finish Relationship is a Mathematical Practical Concept Start to Finish (SF) Relationship is probably one of the most confusing scheduling concept. It is not a profound concept but students still find it confounding. During my classes, most of the students are able to understand first 3 PDM Relationships easily. There are seldom any […]

Continue reading

What is the Difference Between Project Effort and Duration?

project duration and effort

I recently posted a series of articles on Project Network Diagrams. I wrote an article on Start to Start Relationship. I described the relationship using a small example. While explaining the example I wrote a statement – “The Project Team will need a total of 3 days to complete these activities”. A very senior Project […]

Continue reading

9 Frequently Asked Questions on Lead and Lag

lead and lag

Lead and Lag Demystified There are many terms that perturb project management professionals. Lead and Lag are two such terms. I interact with many professionals on a regular basis. I often find that many of them are not fully aware of meaning of these terms. Even though they know the correct definitions of these terms, […]

Continue reading

How to Use Leads and Lags in Project Schedule?

lead lag

Leads and Lags – Definitions, Explanations & Examples Leads and Lags are essential for making a good project schedule. They are the basic building blocks of scheduling. Many scheduling experts don’t use them. Instead, they often apply (incorrect) alternatives. In my opinion, Leads and Lags are easy to use and implement. They should always be […]

Continue reading

Start to Finish Relationship In Project Management – Definition & Examples

start to finish

Start to Finish Relationship in Project Management In this article, I have defined and explained Start To Finish Logical Relationship with the help of Project Network Diagrams, Gantt Charts & Examples. Start to Finish (SF) is one of the four relationships described in Precedence Diagramming Method (PDM). The other three are: Finish to Start (FS) […]

Continue reading

Finish to Finish Relationship In Project Management – Definition & Examples

finish to finish

PDM Relationships – Finish to Finish This article extends my previous article on Project Network Diagram. Project Network Diagrams are used to pictorially represent Project Schedule and Project Dependencies. You can also read my other articles on Project Dependencies – What are Project Dependencies and 4 Types of Project Dependencies. There are many ways to […]

Continue reading
1 2 3