PD005 – Difference between PMBOK 4th and 5th ed

Previous Post – “PD004 – Difference between PMBOK 4th and 5th ed”

Change XVII

Process Group – Planning / Knowledge Area – Communications 

Instead “Plan Communications” now it is “Plan Communications Management”
Inputs: Project management plan is added. Stakeholder management strategy is removed.

Tools and Techniques: Meetings is newly added.

Change XVIII

Process Group – Planning / Knowledge Area – Risk

“Plan Risk Management” 
Inputs: Project management plan, Project charter and Stakeholder register are newly added. Project scope statement, Cost management plan, Schedule management plan and Communication management plan are removed.

Tools and Techniques: Analytical techniques, Expert judgment and Meetings are newly added. Planning meetings and analysis is removed.

Change XIX

Process Group – Planning / Knowledge Area – Risk

“Identify Risk” 
Inputs: HR Management Plan, Scope Baseline and Procurement documents are newly added.

Change XX

Process Group – Planning / Knowledge Area – Risk

“Perform Qualitative Risk Analysis” 
Inputs: Scope Baseline and Enterprise Environmental Factors are newly added. Project scope statement is removed.

Outputs: Project document updates newly added. Risk register updates is removed.

Change XXI

Process Group – Planning / Knowledge Area – Risk

“Perform Quantitative Risk Analysis” 
Inputs: Enterprise Environmental Factors newly added.

Outputs: Project document updates newly added. Risk register updates removed.

Change XXII

Process Group – Planning / Knowledge Area – Risk

“Plan Risk Response” 
Outputs: Risk register updates and Risk related contract decisions are removed.

Change XXIII
 
Process Group – Planning / Knowledge Area – Procurement

“Plan Procurement Management” 
Inputs: Project management plan and Stakeholder register are newly added. Scope baseline, Teaming agreements, Risk-related contract decisions and Cost performance baseline are removed.

Tools and Techniques: Market Research and Meetings are newly added. Contract types removed.

Outputs: Project documents updates newly added.

Change XXIV

Process Group – Planning / Knowledge Area – Stakeholder [Newly added KA]

“Plan Stakeholder Management” [Newly added process] 
Inputs: Project management plan, Stakeholder register, Enterprise environmental factors and Organizational process assets.

Tools and Techniques: Expert judgment, Meetings and Analytical techniques.

Outputs: Stakeholder management plan and Project document updates

Ramanujam VijayaGopal