PD003 – Difference between PMBOK 4th and 5th ed

Last updated on July 21, 2016

Previous Post – “PD002 – Difference between PMBOK 4th and 5th ed

Change V

Process Group – Planning / Knowledge Area – Scope

“Define Scope” 
Inputs: Scope Management Plan newly added

Tool and Techniques: Instead of Alternatives Identification, Alternatives Generation added
Change VI

Process Group – Planning / Knowledge Area – Scope

“Create WBS”
Inputs: Scope Management Plan newly added

Outputs: WBS and WBS dictionary removed as separate outputs

Change VII

Process Group – Planning / Knowledge Area – Time

A New Process “Plan Schedule Management” Added
Inputs: Project Management Plan, Project Charter, Enterprise environmental factors and organizational process assets

Tool and Techniques: Expert Judgement, Analytical techniques and Meetings

Outputs: Schedule Management Plan

Change VIII

Process Group – Planning / Knowledge Area – Time

“Define Activities”
Inputs: Schedule Management Plan newly added.

Tool and Techniques: Templates removed

Change IX

Process Group – Planning / Knowledge Area – Time

“Sequence Activities”
Inputs: Schedule Management Plan newly added.

Tool and Techniques: Schedule Network Templates removed

Ramanujam VijayaGopal
blogville

We are now in Ckalari.com
We are now in Ckalari.com
Praveen Malik, PMP is a certified Project Management Professional (PMP®) with a rich 20+ years of experience. He is a leading Project Management Instructor and Consultant. He regularly conducts Project Management workshops in India & abroad.

Leave a Reply

Your email address will not be published. Required fields are marked *